There's also been progress on important steps that we can't see, but move the project forward. All of the revised plans are pending with the County, and we have addressed the minor comments we received from County staff. We have reviewed all of the equipment specifications and equipment is on order -- from the pumps, filters, and the storm water management system to the new light poles, lifeguard chairs, and backstroke flags.
The weather has been beautifully cooperative, the "Overrlee ghost" stories in the papers haven't scared away any more workers, and, most important, the work has proceeded safely and on budget. We are confident that the phased opening of the pools beginning at the end of May is still a realistic goal. The warm weather and the project taking shape is heightening our anticipation for the coming season -- we can hardly wait!